... and we're ready to play!
WE'RE REBUILDING COMMUNITY
DECEMBER 2009
SITE OF DESTROYED PLAYGROUND HAS BEEN REPAIRED AND ALL REMINDERS ARE NOW REMOVED
JANUARY 2010
NEW SITE HAS BEEN DECIDED AND WE ARE PLACING THE EQUIPMENT AROUND THE CURRENT OUTDOOR CLASSROOM ON NORMANDY STREET
FEBRUARY 2010
EQUIPMENT AND DESIGN HAS BEEN FINALIZED
MARCH 2010
PROJECT HAS BEEN SUBMITTED TO TENDER BY HRM
MAY 2010
CONTRACT AWARDED TO PLAYPOWER. PLAYGROUND EQUIPMENT HAS BEEN ORDERED. DELIVERY EXPECTED IN 4 WEEKS. CONSTRUCTION TO FOLLOW SHORTLY AFTER IN EARLY JULY.
JULY 2010
REBUILDING!
SITE OF DESTROYED PLAYGROUND HAS BEEN REPAIRED AND ALL REMINDERS ARE NOW REMOVED
JANUARY 2010
NEW SITE HAS BEEN DECIDED AND WE ARE PLACING THE EQUIPMENT AROUND THE CURRENT OUTDOOR CLASSROOM ON NORMANDY STREET
FEBRUARY 2010
EQUIPMENT AND DESIGN HAS BEEN FINALIZED
MARCH 2010
PROJECT HAS BEEN SUBMITTED TO TENDER BY HRM
MAY 2010
CONTRACT AWARDED TO PLAYPOWER. PLAYGROUND EQUIPMENT HAS BEEN ORDERED. DELIVERY EXPECTED IN 4 WEEKS. CONSTRUCTION TO FOLLOW SHORTLY AFTER IN EARLY JULY.
JULY 2010
REBUILDING!